Version of this project
Factory within the existing mill to produce Molded Fiber.
Construction time 4-4,5 months from delivery to finished MEP.
Measurements 25*25*5,8
CLT VI 145 m3 and 490 m2 CLT Rib panels
Area (m²) | 900 |
Products | CLT, CLT rib panel |
Product quality | VI |
Product volume (m³) | 195 |
Developer | Stora Enso |
Architect | Sweco Architects AB |
Structural Engineer | Sweco Structures |
MEP Designer | Sweco |
Main contractor | AF Bygg SYD |
Specialist Timber Contractor | AF Bygg SYD |
Construction duration (months) | 2 |
Timber superstructure erection duration (weeks) | 2 |