Version of this project
Close to the Issy-les Moulineaux fortress near Paris, this 1 550 m² building with 23 flats has been finalized and fits perfectly into the environment. The structure consist of CLT by Stora Enso and glulam, and has been certified by the BBCA association as a low carbon building. The construction time was only 11 month (including 4 weeks for the CLT) and 649 m³ of CLT by Stora Enso have been used.
Residential Multi-storey Building Concept by Stora Enso
Multi-storey buildings in massive wood are high-performing, renewable structures that can help to meet the growing demand for new urban buildings and more efficient, sustainable construction.
Click here to learn more about our residential multi-storey building concept.
| Area (m²) | 1,550 |
| Storeys | 3 |
| Units | 23 |
| Products and Services | Sylva™ CLT Floors and Roofs, Sylva™ CLT Stairs |
| Product quality | Visible quality (VI) |
| Product volume (m³) | 649 |
| Product delivery duration (weeks) | 4 |
| Number of deliveries | 15 |
| Partner of Stora Enso | Woodeum |
| Developer | Woodeum |
| Architect | Wilmotte & Associés |
| Structural Engineer | Sylva Conseil |
| MEP Designer | Pouget Consultants |
| Main contractor | Bouygues Bâtiment IDF |
| Specialist Timber Subcontractor | Bouygues Bâtiment IDF |
| Construction duration (months) | 11 |
| Timber superstructure erection duration (weeks) | 4 |